The City of Hamilton, Kehoe Marine Construction, and Brian Riggs Engineering are still developing a strategy for the wave attenuation wall.
Kehoe will be installing dive bags and barrels to assist in raising the sunken breakwaters starting Friday May 4th. Please be respectful of the extensive operations with divers in the water by staying clear and keeping your wake to minimum. Please enter the harbour at the west end (coordinates 43°16’34.75″N 79°52’5.97″W) until further notice. Kehoe is hopeful the north breakwater will be up and functioning by Friday May 11th.
Kropf is currently on site with the dock repairs ongoing. The James Street docks have been fully inspected and finger docks will be reinstalled when the wave attenuation wall is back in place. The Iroquois Pier slips are still being inspected and will be operational soon. We will be accommodating all vessels on the James Street docks until Kropf has completed all work on the Iroquois Pier Docks.
The Burlington Skyway Bridge will undergoing some repairs starting Saturday May 5th. This will affect the Burlington lift Bridge operations and the details will be posted on our blog.
We will continue to keep Harbour West website blog updated. If you have any questions, please reach out to Tristen, Lynn, or myself.
Thank You,
Kelly Flood
Marina Manager
[email protected]